From: "Osalbo, Faustino Jun" <fosalbo@oaklandnet.com>
Date: July 5, 2005 3:20:45 PM PDT
To: 'Mark Brest van Kempen' <mbvk@sbcglobal.net>
Cc: "Brooks, Desley" <DBrooks@oaklandnet.com>, "Nadel, Nancy" <NNadel@oaklandnet.com>, "Uzegbu, Marcel" <MUzegbu@oaklandnet.com>,  "Estes, Lesley" <lcestes@oaklandnet.com>, "Schwarz, Alison" <aschwarz@oaklandnet.com>, "'klichten@waterboards.ca.gov'" <klichten@waterboards.ca.gov>, "'friendsof2creeks@yahoogroups.com'" <friendsof2creeks@yahoogroups.com>, "'nannystu@pacbell.net'" <nannystu@pacbell.net>, "Neary, Mike" <mjneary@oaklandnet.com>,  'Barbara Sutherland ' <IMCEAMAILTO-bsutherland+40ucdavis+2Eedu@oaklandnet.com>,  Office of the Mayor <OfficeoftheMayor@oaklandnet.com>,  "'gantenbein@n-h-i.org'" <gantenbein@n-h-i.org>, "'chiye@cazuma.com'" <chiye@cazuma.com>, "Ward, Ron (PWA)" <rgward@oaklandnet.com>,  "Lau, David W" <dwlau@oaklandnet.com>, "Sweiss, Fuad" <fssweiss@oaklandnet.com>, "'jean@jeanquan4council.org'" <jean@jeanquan4council.org>, "'cityochang@aol.com'" <cityochang@aol.com>,  "Madison, William" <wmadison@oaklandnet.com>

Subject: RE: Chimes Creek increased flow

Mark,
On Monday, June 27th, the water in the detention pond was measured to be 5 NTU and DeSilva Gates was allowed to discharge directly into the City's storm drain system. The pump used for this discharge is a floating 4" pump with a capacity of 500 gallons per minute. The pumping of the detention was from 830am until 230pm that day. DeSilva Gates plans to discharge the water from the pond one day every two weeks to keep the detention pond drained. 

Jun Osalbo